is excited to announce the reconstruction of the Resch Family East River Trail
in Green Isle Park. This work will begin
the week of August 14th and is scheduled to be completed by
September 22nd if everything runs smoothly.
The project will
consist of removing the old sections of trail from the bridge on the northeast
side of the park around the west and south sides of the park. There are a few other short sections of trail
by the tennis courts and in the woods that are part of the project as
well. The new trail will be a ten foot
wide multi-use asphalt trail similar to the section that was reconstructed
between Green Isle Park and Wiese Park in 2014.
Sections of the trail
will be closed while the contractor is preforming work but should be accessible
during the times that the contractor is not on site. For additional information or questions on
this project please contact the Village of Allouez Parks, Recreation, and
Forestry Department at 448-2800 or the consulting engineer, Craig Schuh, from
Ayres Associates at 498-1200.