2019 Street Reconstruction – Project Schedule


This spring the Village of Allouez will begin reconstructing the following streets:
  1. Longview Ave. –Delahaut St. to Libal St.
  2. Oakwood Ave. – Greene Ave. to Allouez Ave.
  3. Oak Hill Dr. – Beaumont St. to Oakwood Ave.
  4.  Summit St. – Beaumont St. to Oakwood Ave.
  5. Martha Ave. – Dead End south 60 feet (New Construction) 
  6. St. Joseph St. - Riverside Dr. to Webster Ave.  

This reconstruction project includes:
  •  Replacement of the existing watermain, sanitary and storm sewer where necessary. 
  • Removal and replacement of existing water, sanitary and storm sewer laterals to the property line.
  • Placement of new concrete curb & gutter and driveway aprons.  The existing driveway width at the property line will be matched.
  •  Removal and replacement of the asphalt pavement. Installation of new sidewalk on Longview Ave (northside only) and St. Joseph St. (both sides).
  • Voluntary replacement of private side sanitary sewer lateral.

Longview Ave. – Delahaut St. to Libal St.

Weather permitting the anticipated project schedule is as follows:
  • Work to Begin – Middle of June
  • Substantial Completion Date – End of August

Project Status:

Work has not started.



Martha Ave. – Dead End south 60 feet (New Construction)

Weather permitting the anticipated project schedule is as follows:
  • Work Started – May 13th
  • Substantial Completion Date – End of August

The installation of underground utilities and laterals have been installed and are in service.  The contractor to hold off the grading of the roadway, placement of base aggregate, curb and gutter and pavement until after the basements of the abutting homes have been constructed. 



St. Joseph St. - Riverside Dr. to Webster Ave. 

Weather permitting the anticipated project schedule is as follows:
  • Work Stared– May 20th
  • Substantial Completion Date – Middle of September

Project Status (06/03/19):

Street closed to thru traffic.  Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. 



With exception of the trunk-line storm sewer, the underground utilities and laterals are installed at the west end of the project.  This week the contractor will be renewing (removing and replacing) services and installing storm sewer from Riverside Drive to middle third of the project. 



Oakwood Ave. – Greene Ave. to Allouez Ave.

Weather permitting the anticipated project schedule is as follows:
  • Work to Begin – Beginning of July
  • Substantial Completion Date – Middle to end of October

Project Stutus:

Work has not started.



Oak Hill Dr. – Beaumont St. to Oakwood Ave.

Weather permitting the anticipated project schedule is as follows:
  • Work to Begin – Beginning to Middle of August
  • Substantial Completion Date – Middle to end of October

Project Stutus:

Work has not started.



Summit St. – Beaumont St. to Oakwood Ave.

Weather permitting the anticipated project schedule is as follows:
  • Work to Begin – End of July
  • Substantial Completion Date – Middle to end of October

Project Stutus:

Work has not started.