Saturday, September 14, 2019

2019 Street Reconstruction – Project Schedule


The construction season has begun in The Village of Allouez on some or all of the streets listed below:
1. Longview Ave. –Delahaut St. to Libal St.
2. Oakwood Ave. – Greene Ave. to Allouez Ave.
3. Oak Hill Dr. – Beaumont St. to Oakwood Ave.
4. Summit St. – Beaumont St. to Oakwood Ave.
5. Martha Ave. – Dead End south 60 feet (New Construction)
6. St. Joseph St. – Riverside Dr. to Webster Ave.

7. Brookridge St. – Libal St. to Dauphin St.
8. Beaupre St. – Libal St. to Webster Ave.
9. Warren Court – Riverside Dr. to Du Charme Ln.
This reconstruction project includes:
– Replacement of the existing water main, sanitary and storm sewer where necessary.
– Removal and replacement of existing water, sanitary and storm sewer laterals to the property line.
– Placement of new concrete curb & gutter and driveway aprons. The existing driveway width at the property line will be matched.
– Removal and replacement of the asphalt pavement.
– Installation of new sidewalk on Longview Ave (north side only) and St. Joseph St. (both sides).
– Voluntary replacement of private side sanitary sewer lateral.
Longview Ave. – Delahaut St. to Libal St.
Weather permitting the anticipated project schedule is as follows:
• Work Started – June 24

• Substantial Completion Date – End of August/Early September
Project Status:
-Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.
-Final layer of asphalt is next on the schedule and should be completed this week.
Martha Ave. – Dead End south 60 feet (New Construction)
• Work Started – May 13th

• Substantial Completion Date – Mid-September


Project Status:
-Paving and landscaping is next on the schedule.
St. Joseph St. – Riverside Dr. to Webster Ave.
Weather permitting the anticipated project schedule is as follows:
• Work Started– May 20th
• Substantial Completion Date – Middle of September
Project Status:
-Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.
-The installation of street signs is next on the schedule.
Oakwood Ave. – Greene Ave. to Mission Road
Weather permitting the anticipated project schedule is as follows:
• Work Started June 24

• Substantial Completion Date – Middle to end of October
Project Status:
-Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. Temporary mailboxes are set up for use.
-Road excavation is scheduled to begin the week of September 3 with curb & gutter to follow.
Oakwood Ave. –Mission Road to Allouez Ave.
Weather permitting the anticipated project schedule is as follows:
• Work Started– Sept 3
• Substantial Completion Date – Middle to end of October
Project Status:
-Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. Temporary mailboxes are set up for use.

-The contractor to begin with the installing of new water main at the Mission Road intersection. Sanitary sewer main line to follow.
Oak Hill Dr. – Beaumont St. to Oakwood Ave.
Weather permitting the anticipated project schedule is as follows:
• Work started Aug 12
• Substantial Completion Date – Middle to end of October

Project Status:
-Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.
-Private side sanitary sewer laterals to be installed the week of September 9 with street excavation to follow.
Summit St. – Beaumont St. to Oakwood Ave.
Weather permitting the anticipated project schedule is as follows:
• Work Started Aug 28
• Substantial Completion Date – Middle to end of October

Project Status:
-Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.
-The contractor to continue working on the installation of sanitary sewer main. Water services and sanitary sewer laterals to follow.


Brookridge St. – Libal St. to Dauphin St.
Weather permitting the anticipated project schedule is as follows:
• Work started 8/19/19
• Substantial Completion Date – End of August/Early September
Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction.
Final layer of asphalt and landscaping is next. Paving will be scheduled around the drop-off and pick up of students.
Beaupre St. – Libal St. to Webster Ave.
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – Approximately 9/16/19
• Substantial Completion Date – Middle to end of October
Project Status:
Work has not started.

Warren Court – Riverside Dr. to Du Charme Ln.
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – Approximately 9/16/19
• Substantial Completion Date – Middle to end of October
Project Status:
Work has not started.