Monday, October 14, 2019

2019 Street Reconstruction – Project Schedule

The construction season has begun in The Village of Allouez on some or all of the streets listed below:
  1. Longview Ave. –Delahaut St. to Libal St.
  2. Oakwood Ave. – Greene Ave. to Allouez Ave.
  3. Oak Hill Dr. – Beaumont St. to Oakwood Ave.
  4. Summit St. – Beaumont St. to Oakwood Ave.
  5. Martha Ave. – Dead End south 60 feet (New Construction)
  6. St. Joseph St. – Riverside Dr. to Webster Ave.
  7. Brookridge St. – Libal St. to Dauphin St.
  8. Beaupre St. – Libal St. to Webster Ave.
  9. Warren Court – Riverside Dr. to Du Charme Ln.
  10. Blackhawk Drive – Libal Street east 250 ft.
This reconstruction project includes:
  • Replacement of the existing water main, sanitary and storm sewer where necessary.
  • Removal and replacement of existing water, sanitary and storm sewer laterals to the property line.
  • Placement of new concrete curb & gutter and driveway aprons. The existing driveway width at the property line will be matched.
  • Removal and replacement of the asphalt pavement.
  • Installation of new sidewalk on Longview Ave (north side only) and St. Joseph St. (both sides).
  • Voluntary replacement of private side sanitary sewer lateral.
Longview Ave. – Delahaut St. to Libal St.
Project Status:
Street opened to traffic. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners
Martha Ave. – Dead End south 60 feet (New Construction)
• Work Started – May 13th
• Work Completed – September 13
Project Status:
Street opened to traffic. Contractor will monitor the progress of the turf restoration. Lawns to be mowed as needed by property owners
St. Joseph St. – Riverside Dr. to Webster Ave.
• Work Started– May 20th
• Work Completed
Project Status:
Street opened to traffic. Contractor will monitor the progress of the turf restoration. Street signs to be installed the week of October 7. Lawns to be mowed as needed by property owners.
Oakwood Ave. – Greene Ave. to Mission Road
Weather permitting the anticipated project schedule is as follows:
• Work Started June 24
• Substantial Completion Date – Middle to end of October
Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. Temporary mailboxes are set up for use.
Installation of driveway aprons will continue from St. Matthews to Mission Road. Driveway aprons will be opened from Greene to St. Matthews St. Wednesday/Thursday. MCC will be grading the road from Greene to Mission with paving on Thursday/Friday. Final landscaping and all touch-ups to follow.
Oakwood Ave. –Mission Road to Allouez Ave.
Weather permitting the anticipated project schedule is as follows:
• Work Started – Sept 3
• Substantial Completion Date – Middle to end of October
Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. Temporary mailboxes are set up for use. Private side sanitary sewer lateral installation to continue till mid-week. Road excavation to begin mid-week with curb & gutter placement to follow.
Oak Hill Dr. – Beaumont St. to Oakwood Ave.
Weather permitting the anticipated project schedule is as follows:
• Work started Aug 12
• Substantial Completion Date – Middle to end of October
Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. Driveway apron to be installed the week of October 7 with grading and paving to follow.
Summit St. – Beaumont St. to Oakwood Ave.
Weather permitting the anticipated project schedule is as follows:
• Work Started Aug 28
• Substantial Completion Date – Middle to end of October
Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes, businesses and residents during construction. Driveway apron to be installed the week of October 7 with grading and paving to follow.
Brookridge St. – Libal St. to Dauphin St.
• Work Started — August 19
• Work Completed – September 7
Project Status:
Street opened to traffic
Beaupre St. – Libal St. to Webster Ave.
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – September 23
• Substantial Completion Date – October 3rd
Project Status:
Roadway has been paved, turf restoration is next of the schedule.
Warren Court – Riverside Dr. to Du Charme Ln.
Weather permitting the anticipated project schedule is as follows:
• Work to Begin – Approximately 9/23/19
• Substantial Completion Date – Middle to end of October
Project Status:
Road excavation to continue till mid-week with curb and gutter installation to follow.
Blackhawk Drive – Libal Street east 250 feet.
Weather permitting the anticipated project schedule is as follows:
• Work Started October 2nd
• Substantial Completion Date – November 1st, 2019
Project Status:
Street closed to thru traffic. Roadway (one lane) will be open for emergency purposes and residents during construction. Underground utility work to be completed Monday/Tuesday. Roadway excavation, concrete curb and gutter and driveway aprons to follow.

1 comment: