2020 Reconstruction Project Update


2020 Street Reconstruction – Project Schedule
July 7, 2020
This 2020 construction season has begun in The Village of Allouez on some or all of the streets listed below:
1. St Mary’s Boulevard -- Riverside Dr to  ± 1500 feet to east (#310/#311)
2. Stanton Court/Arbor Lane --  Stanton Ct to Rosemont Dr (near Webster Ave)
3. Garland Street – Webster Ave to Baird St
4. Allouez Terrace Alley – Riverside Dr to end.
5. East St Joseph Alley - behind Associated Bank
6. Olde River Condominium Trail
7. Longview Pond Trail Repair
8. Bethel Pond Project
9. Standpipe (Water Tower) Repair Project
These street improvements include:
- Removal and replacement of the asphalt pavement.
- Replacement of defective gravel base
- Replacement of defective concrete curb & gutter and driveway aprons
- Manhole & catch basin repairs

- Sanitary sewer repairs on St Mary’s Blvd

1. St Mary’s Boulevard – Riverside Dr to ± 1500 feet to east (#310/#311)
Weather permitting the anticipated project schedule is as follows:
• Work started – May 7
• Substantial Completion Date – Beginning of June (paving only/sanitary work will continue)
Project Status:
Initial paving completed (6-2-20) proposed sewer work schedule is as follows:  sanitary sewer main lining to be completed by September 4.  Sanitary sewer lateral replacements project to begin August 31 and be completed by October 2.  Final paving and turf restoration to be completed by October 30, 2020.  


2. Stanton Court/Arbor Lane -- Stanton Ct to Rosemont Dr (near Webster Ave)
Weather permitting the anticipated project schedule is as follows:
• Work started – May 13
• Worked completed – June 26
Project Status:
Paving completed; contractor & village to monitor the progress of the restored landscaping.


3. Garland Street – Webster Ave to Baird St
Weather permitting the anticipated project schedule is as follows:
• Work started – May 28
• Worked completed – June 26
Project Status:
Paving completed; contractor & village to monitor the progress of the restored landscaping.


4. Allouez Terrace Alley – Riverside Dr to end.
Weather permitting the anticipated project schedule is as follows:
• Work started  – May 14
• Worked completed – June 16
Project Status:
Paving completed contractor will return to install gravel shoulder.


5. East St Joseph Alley behind Associated Bank
Weather permitting the anticipated project schedule is as follows:
• Work started – May 14 (asphalt removal)
• Worked completed – June 16
Project Status:
Paving completed.


6. Olde River Condominium Trail
Weather permitting the anticipated project schedule is as follows:
• Work to Begin as weather permits
• Worked completed – June 16
Project Status:
Paving & shouldering completed contractor will return for turf restoration.


7. Longview Pond Trail Repair
• Worked completed – June 15


8. Bethel Pond Project
Beginning in July the Village will be constructing a 1-acre regional stormwater pond located east of the Bethel Baptist Church on the southside of Kalb Street.  In conjunction with the project, the Village will be installing 1350 ft of 48” Storm Sewer along the south southside of Kalb Street from Irwin Avenue  east to the pond.
The anticipated project schedule is as follows:
• Work to Begin – End of July
• Substantial Completion Date – September 25th, 2020
The Village will be constructing a 1-acre regional stormwater pond located east of the Bethel Baptist Church on the south side of Kalb Street.  In conjunction with the project, the Village will be installing 1350 ft of 48” Storm Sewer along the south southside of Kalb Street from Irwin Avenue  east to the pond.
Project Status:
Work has started with the removal of trees and the installation of erosion control measures.  Next on the schedule will be the construction of the pond (2-3 weeks) with storm sewer main to follow. 

9. Standpipe (Water Tower) Repair Project
Minor structural repairs to the Water Tower are anticipated to begin on the 13th of July.  In general the interior and exterior repairs consist of replacement of the overflow weir box, exterior power washing, touch-up painting, improvements to the fall protection equipment, and upgrading at grade overflow pipe. 

The anticipated project schedule is as follows:
• Work Started Mid - July
• Worked Completed – August 6
Project Status:
Work has been completed and we are back to normal operations.